Integration of 93 machines to a Production Line, HMI Standardization.

Objective:

A manufacturing plant specializing in blood glucose strip production was expanding its operations by adding 93 machines to a production line. The new equipment would have to be installed and configured in the plant’s existing SCADA system to have complete integration.

Solution:

Our engineers provided PLC and HMI programming as well as instrumentation procurement and SCADA system upgrades. We also standardized the HMI screens, making them visually consistent throughout the plant for ease of operation.

Results:

This solution complied with the FDA’s 21 CFR Part 11 regulations and delivered seamless interconnection.